Pump Stations & Piping

Pump Stations & Piping

We Are Specialized in piping works, skid manufacturing. SWCC SAUDI ARABIA. Shuqaiq phase2 of 400,000 Dia. Inch piping work have been successfully done by our team. For this purpose 2000m2 spool shop was built and equipped. Pump station mechanical Work Scope was also carried. 96% of the work scope completed in 2 years of time under company MIPE Co. Occupation: General Manager
PUMP STATION AT SHUQAIQ PHASE2 PROJECT. MAIN CLIENT:SWCC SAUDI ARABIA. ALL MECHANICAL WORK INSTALLATIONS, SPOOLWORK’S FABRICATION WERE DONE
PUMP STATION AT SHUQAIQ PHASE2 PROJECT. MAIN CLIENT:SWCC SAUDI ARABIA. ALL MECHANICAL WORK INSTALLATIONS, SPOOLWORK’S FABRICATION WERE DONE
SPOOL/ PANTALOON FABRICATION AT SHUQAIQ WORK SHOP
VALAVE STATION AT SHUQAIQ PHASE2 PROJECT. MAIN CLIENT:SWCC SAUDI ARABIA. ALL MECHANICAL INSTALLATION ,SPOOLWORKS FABRICATION AND INSTALLATION WERE DONE